- Hooksett Public
Library
- Board of
Trustees
- April 13, 2004 9:00
AM
- Minutes
Present: Marion Jacobi, President, Mary Farwell, Secretary,
Ann Marie Van De Water, Treasurer, Fran Hebert, Library Director
Secretary's Report: Minutes from the March 9, 2004 meeting
were approved with one revision and filed
Treasurer's Report: Treasurer's report was reviewed
- AV reported that we have a rate lock with Energy North.
- AV reported that she is working with the Government &
Banking Dept at Bank of NH to set up payment of online taxes by
the bookkeeper
- AV researched expenditures from the Programming line and made
some adjustments which better reflect the actual
expenditures
- AV handed out a projection of the wage line. Projected
over-expenditure of this line is due to the necessity of paying
Pat Cate's accumulated vacation time and the overlap with Mark.
Trustees noted that we need to determine the amount needed to pay
Fran for her accumulated vacation time as well
- Trustees reviewed upcoming expenditures to Maintenance line
including electrical issues
Library Director's Report:
- Circulation report was distributed.
- Humanities program is scheduled for May. Topics include Storm
Clouds over Iraq ( May 6), War and Peace in the Middle East (May
13), and Geography of the Middle East May 20) with Emphasis on
Oil and Water Resources.
- Financial Issues for Women is scheduled for May 18 and May
25
- Computer Upgrade - If we have sufficient monies in the budget,
J Scott is recommending replacement of the two circulation desk
computers to comply with the needs for the new Horizon system.
($1467) He is also recommending memory upgrades for staff
computers ( $663.65)
Old Business:
- HVAC Report- John Karpinski (IES) gave a verbal report of
possible options for remediation or replacement of existing HVAC
system.
- The existing system provides for 32.5tons cooling with
allowance for 150 people, based on the physical characteristics
of the building. Thus, we could use a 35 ton system as the
calculation includes all areas of the building.
- The outside condenser is presently operating on a single
coil, which puts us in jeopardy of losing our air conditioning
if this coil fails.
- Some rooms have up to three thermostats which is very
inefficient. There are 55 controls on the 2nd floor and 66 on
the 1rst floor. Controls could be thermostats, valves that
control heat to convectors or reheat coils. After the project
is finished, controllers need to calibrated once yearly.
- We have one control diagram but at one time there must
have been books ( Pneumatic Controls Manual, Operating
Maintenance Manual) which detailed each controller and
pneumatic tubing. FH to check with Chris at SNHU and anyone
else who might have seen such books
- John presented two options for remediating our HVC problems
- OPTION 1
- A. Phase 1 35 ton refrigeration system for cooling-
convert air handling unit ( motors and drives) to handle
13 tons, rather than the 22.5 they are handling now.
- B. Phase 2 Convert all controllers. Install 21 VAV (
variable air boxes). Match up flow stations that measure
air in and out from supply side and return side. In
essence, we are converting our existing constant volume
system to a variable volume system. This system will
require constant maintenance.
- OPTION 2
- A. Install a rooftop VAV 20 ton system for the 2nd
floor
- B. Lower level
- 1. Install another VAV rooftop system need to use
a 20 ton rooftop for 15 ton load as there are no 15
ton systems
- 2. Retain lower level as constant volume
system.
- Option 2 is better for future maintenance and
reliability but it all must be done at once. He also
recommended that we ask Delta for a list of issues that need
to be repaired, ranked by their criticality and the costs
associated with each repair.
- AED- MF reported a conversation with Kathy Raymond from CMC.
They are not familiar with alarming the location of the AED, not
provisions for hanging it on a wall.. CMC is working on paperwork
which needs to precede delivery of the unit. Paperwork will be
sent for review and then the unit will be delivered. Trustees
want the unit to be accessible but protected so agreed to seek
advice from Atlantic Security once the unit is delivered.
- Fire Alarm Monitoring- MJ reported that Atlantic Security has
done a survey of the building and found some deficiencies that
need to be corrected ( see attached report). Total cost of pull
stations, annunciator, motion detector and testing of emergency
lights to be $1307, to be expended from Maintenance line. There
should also be an annual inspection, cost $700 per year which
would include $75 for any needed parts replacement.
- Fire Extinguishers: Lee from Concord Fire Extinguisher
visited and reported that we only need two new fire extinguishers,
at $68 per unit, to be compliant with NFPA codes. His office
will send a letter to that effect, which will be forward to the
Fire Department to be placed in our file.
- HVAC Warrant Article-: The Town Budget Committee voted to
recommend our warrant article. Trustees decided that it would be
advantageous to have library representatives outside the polls to
pass out an informative piece about our HVAC problems. MF to
recruit volunteers to pass out materials and MJ to look at
revising Karpinski letter to brief "talking points" sheet
- SNHU Continuum- MF emailed information to former SNHU
Continuum director. She will make best effort to distribute, but
she has some immediate medical issue which will put further
contact on hold for awhile.
- Rear Parking Lot: Wes thinks it is ok but he will check with
Dale Hemeon and trustees will review issue again in the
spring.
- Staff job descriptions have been updated and are in a red
binder in Fran's office
- FH is compiling a list of vendors and a calendar of
maintenance tasks and when they are normally performed.
New Business:
- New Signage: MJ reported that, due to the proposed new
development to the rear of the library, the driveway to the
library may be moved and we will need to investigate new signage
at some point in the future when the location of the new driveway
has been defined.
Issues we are tracking:
- Rear Parking Lot: Wes thinks it is ok but he will check with
Dale Hemeon and trustees will review issue again in the
spring.
The next regular meeting of the Trustees will be May 12 at 9
AM